Bore hole Water Treatment Project:The bore hole was located in a food factory. Due to the high levels of pesticide in the water the bore hole only served the wash down facility. Iron filters and a pumping system existed. The pumps were designed for the flow rate required for wash down only and were reused as dedicated back wash pumps and new booster pumps installed. The control panel was replaced with a panel that combined the existing iron filter requirements with the new pesticide removal system. |
|
Existing Parameters:
New parameters:
Balba Technologies Provided:
|
![]() ![]() |
The project was delivered on time with no disruption to production and resulted in high ongoing savings on water costs. |
|
![]() |
|